1) The issuer must stop work if ……….
a. The issuer leaves the job site.
b. More men are working than stated on the permit.
c. The site was found to be unsafe.*
d. The issuer looses his copy of the permit.
a. The issuer leaves the job site.
b. More men are working than stated on the permit.
c. The site was found to be unsafe.*
d. The issuer looses his copy of the permit.
2) A pipe fitter cannot work on the same pieces of equipment using welder’s permit because.
a. Welder’s are usually contractors.
b. Gas tests are not needed for pipefitters.
c. Each type of work involves different hazards.*
d. Joint site inspections are not needed for pipefitters.
3) If a work permit is not issued during an emergency, what must be done to do the work?
a. Superintendent must approve.
b. All safety precautions must be taken.*
c. Wear Scott air Pak.
d. Joint site inspection.
4) The Receiver must be stop work if ………………. .
a. He cannot find the issuer.
b. The work site becomes unsafe.*
c. The issuer leaves the site.
d. The designated representative must leave.
5) Which of the following is not a restricted area?
a. Tank farm
b. Loading pier.
c. Dump site. *
d. Gasoline station.
6) What is the purpose of the work permit system?
a. To insure that hot work is not done in restricted area.
b. To authorize specific construction or maintenance work. *
c. To document where receiver start work for time keeping.
7) What do you call an area where work permits are required?
a. Restricted area. *
b. Sensitive area.
c. Controlled area.
d. Dangerous area.
8) Who must sign a permit issued for to 30 days?
a. Receiver and designated representative.
b. Operation and maintenance division heads. *
c. Designated representative
d. Operations foreman, issuer and receiver.
9) Who is the check list section important to issuer and receiver.
a. It tells them all the precautions to take.
b. It make sure important steps have been taken.*
c. It defines the duration and scope of work.
d. It controls the receiver’s break time.
10) Which work permit requires sewer to be covered within 75 feet?
a. Entry
b. Cold
c. Hot*
d. Release
11) Who is responsible for safety at the work site after a permit has been extended?
a. The original issuer and receiver.
b. The person who countersigned the permit.
c. The one who originally did the joint site inspection
d. The issuer and receiver who signed the extension.*
12) What happens if work must continue past the time the original permit was to expire?
a. Extend the permit or issue a new one.*
b. Work can continue until the job is completed.
c. Stop work and came back next day.
d. Keep working but tell the issuer.
13) What are the basic precautions for confined space entry, select all items that apply.
a. A sign a standby man, install lighting, install air mover.*
b. Take gas test.*
c. Isolate, clean and purge equipment.*
d. Use PPE.*
14) A release of hazardous liquids or gases permit is required when?
a. Operators release hydrocarbons to the flare.
b. Crafts man builds a scaffold.
c. Pipefitters open a line or install blinds.*
d. Operation drain equipment.
15) What hazard would you find when doing hot work?
a. Auto ignition temperature.
b. Ignition source.*
c. Ignition switch.
d. Ignition point.
16) We use work permit in hazardous areas to identify …………
a. Expired permit.
b. Alternated representative.
c. The designated representative.
d. Hazards and precautions.*
17) The use of a vehicle in an operating area requires, which work permit?
a. Entry
b. Hot *
c. Cold
d. Release
18) What are the basic precautions for cold work? Select all items that apply?
a. Gas test.
b. PPE, barricade and warning signs.*
c. Special work precautions.
d. Standby man.
e. Fire watch.
19) What is oxygen deficiency?
a. A lower than normal amount of oxygen. *
b. Higher than normal amount of oxygen.
c. Less 23.5% oxygen.
d. Oxygen that above it’s flash point.
20) What are the basic precautions for hot work permit? Select all items that apply?
a. Blind, isolate, clean and purge equipment.*
b. Fire watch.*
c. Fire protection equipment*
d. Cover sewer drains.*
e. Gas test.*
21) What is the acceptable level of LEL to allow hot work?
a. 10 to 100 PPM.
b. 0.0 PPM. *
c. 5% to 50%
d. 21% to 23.5%
22) Select the statement where all THREE items are needed before allowing entry into a confine space?
a. Air mover, respirators and countersignatures.
b. Fire watch, air mover, gas test.
c. Gas test. Fire extinguisher, barricades.
d. Lighting, standby man, air mover. *
23) The receiver can leave the job site any time as long as he gets the permeation from his supervisor.
a. True
b. False *
24) Who should keep the work permit?
a. The standby man.
b. The receiver and issuer.*
c. Fire watch.
d. Craft man.
25) What should be a assigned when working near combustible materials?
a. Standby man
b. Fire watch *
c. Fire man
d. Flag man
26) What training should a fire watch have?
a. Operate heavy equipment.
b. Operate control room.
c. Operate fire equipment.*
d. Operate radio equipment.
27) Who should ask for work permit before they start working?
a. The standby man.
b. The receiver.*
c. The fire watch.
d. The issuer.
28) Who should point out all hazards and write on the work permit?
a. The issuer.*
b. The standby man.
c. The fire watch
d. The receiver.
29) Who is responsible for the safety on the work site?
a. The receiver.
b. The issuer.
c. Both issuer and receiver.*
d. Both fire watch and the standby man.
30) What is the purpose of the joint site inspection?
a. To check the availability of equipment and man power.
b. To see the work plan and it is implementation.
c. To discuss the work and identify any hazards and risk.*
d. To meet the works and observe their activities.
31) What must be checked during the joint site inspection? Select all items that apply.
a. Safety devices.*
b. Equipment condition.*
c. Gas test.
d. Attendance report.
32) Who decides whether an area should be restricted or not?
a. The department manager. *
b. The superintendent.
c. The issuer.
d. The receiver.
33) What type of work does the work permit system authorize?
a. Specific construction, maintenance or repair work.*
b. All work constructed for Saudi Aramco.
c. All work done by maintenance or contractors.
d. Non-hazardous work where safety is important.
34) Who is a work permit receiver?
a. A qualified Saudi Aramco employee.
b. A person certified to receive permit.*
c. A person nominated by his supervisor.
d. A maintenance or contract worker.
35) The safety of work site is a sole responsibility of an issuer?
a. True.
b. False.*
36) What responsibility do issuers and receivers share when signing a work permit?
a. Responding to emergency events.
b. Monitoring the operation of process.
c. Maintaining safety conditions at the site.*
d. Getting countersignatures form superintendent.
37) Restricted areas include which locations?
a. Gas plant, tank farms, and assembly areas.
b. Pump station, tank farms, and gas well. *
c. Dining halls housing unites, and operating area.
d. Welding shops pump station, and assembly area.
38) Who can decided that work is a low risk and that a work permit is not needed?
a. The superintendent. *
b. The receiver.
c. The department manager.
d. The issuer.*
39) Who must sign the work permit to close it?
a. Competent person.
b. Issuer and receiver. *
c. Gas tester, issuer and receiver.
d. Designated representative.
40) What must the receiver do if he stops work?
a. Tell the senior crafts man.
b. Tell the designated representative.
c. Tell the issuer. *
d. Tell his immediate supervisor.
41) Work permit can be issued for up to 30 days if ……….
a. The work site is far away.
b. Only cold work will be done.
c. It is highly unlikely that conditions will change. *
d. The receiver cannot close the permit.
42) Who must sign a work permit to extend it?
a. Superintendent’s countersignature is required.
b. The new issuer, receiver and gas tester.
c. The new issuer and receiver. *
d. The new area foreman and the new issuer.
43) “use a fire blanket” or “hand dig only” are example of what?
a. Hazards.
b. Precautionary hazards.
c. Regular precaution.
d. Additional precautions. *
44) Work permit authorize …………
a. Specific work at specific location. *
b. Specific tools at general location.
c. General work at specific plant.
d. General equipment at all work site.
45) Where could an issuer find out which permit to issue for a special job?
a. Facility operating instruments.
b. On the front of any work permit.
c. On the back of any work permit. *
d. Corporate loss prevention manual.
46) The information’s entered in the “extra work location” box is important because it controls?
a. What equipment the receiver can use.
b. Where the receiver can work. *
c. How long the receiver can work.
d. How many worker can be at the job site?
47) What considered cold work?
a. Sand removal and scaffold building. *
b. Brush painting and abrasive blasting.
c. Scaffold building and grinding.
d. Abrasive blasting and painting.
48) What must the issuer do if a join site inspection is not done?
a. Required barricades and warning sign.
b. A sign a designated representative.
c. Tell his foreman.
d. Write why not on the permit. *
49) What must the issuer write in the work permit?
a. Name, badge number and certificate expiry date.
b. Gas test results, name and badge number.
c. Name, organization code and badge number. *
d. Badge number and certificate number.
50) What information must the gas tester enter on the work permit?
a. LTX-310 expiry date, name and badge number.
b. Badge and certification number.
c. Gas test results and normal level.
d. Gas test results, name and badge number. *
51) Any worker can be a sign as standby man?
a. True
b. False. *
52) Why must equipment be de-energized and depressurized before work is started?
a. Accidental start-up could happen. *
b. Purge gas can be lost.
c. Locks and tags will deteriorate.
53) Who install locks and tags first?
a. contractor.
b. Power distribution.
c. Electrical engineer.
d. Operation. *
54) Installing lock and tags on electrical breakers prevents accidental.
a. Blind installation.
b. Start-up of equipment *
c. Nitrogen release.
d. Purging of equipment.
55) The issuer must try to start-up equipment at the field switch after it has been isolated and before work start to make sure.
a. Locks and tags are installed.
b. The receiver’s tag is installed.
c. There is no tag in the area.
d. It cannot accidently start. *
56) How can process equipment be cleaned?
a. Treating and hydro cracking.
b. Closing valves and adding locks
c. Gas testing and steaming
d. Steaming and or water- washing. *
57) Who installs receiver’s locks?
a. One member from each work crew. *
b. The engineer and receiver.
c. The issuer and receiver.
d. Every member of the work crew.
58) When operators change shifts.
a. Their keys are usually transferred to the next shift. *
b. Their tags must be erased.
c. Their locks and tags must be removed.
d. Their locks must be replaced.
59) We isolate equipment to make sure it cannot be.
a. Shut-down on purpose.
b. Shut-down by accident.
c. Taken to a shop for repair.
d. Started-up, leak or cause electrical shock. *
60) Why are hold tag installed?
a. To record gas tests.
b. To record accidents.
c. Explain why the lock is installed? *
d. To identify the issuer and receiver.
61) Removing fuses form an electrical circuit or disconnecting electric wiring is an example of what?
a. Locking
b. Cleaning.
c. Purging.
d. Isolating. *
This comment has been removed by a blog administrator.
ReplyDeleteThis is really helpful for every body
ReplyDeleteAwesome and helpful
ReplyDeleteThis year question & answer send me my mile id
ReplyDeletecrisson0143@gmail.com
ReplyDeletekeshar@sfec.sa.com
ReplyDeleteThank you so much it's very helpfull
ReplyDeleteThanks. It was so helpful
ReplyDeleteRayhan28933@gmail.com
ReplyDeleteThanks a lot of you. It's so beneficial for me
Deleteappreciated
ReplyDeleteI am an ara WPR candidate. I need some important questions and answers for Aramco test. Can anyone send me some important question and answer..
ReplyDeleteNurujjamanshoke@gmail.com give answers this question
ReplyDeleteThank you so much it's very helpfully
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteMohammed Arshad Thanks a lot.
ReplyDeleteThank you so much
ReplyDeleteBig help
ReplyDeletePlease This year questions and answers sand my email
ReplyDeleteirfan1_khanmalkankhan@yahoo.com
I want to job in aramco i did DAE in Mechanical Engineering.
ReplyDeletesuch a helpful
ReplyDelete