Dear all,
Good day, Saudi aramco is the world 4th biggest petrochemical company in the world Yesterday lot of safety friend they comment their email address for saudi Aramco work permit receiver answer so i cant send everyone here i publish the answer of those questions its useful to everyone
Saudi Aramco Work Permit Receiver Q&A
1) The issuer must stop work if ……….
a.
The issuer leaves the job site.
b.
More men are working than stated on the permit.
c. The site was found to be
unsafe.*
d.
The issuer looses his copy of the permit.
2) A pipe
fitter cannot work on the same pieces of equipment using welder’s permit
because.
a.
Welder’s are usually contractors.
b.
Gas tests are not needed for pipefitters.
c. Each type of work involves
different hazards.*
d.
Joint site inspections are not needed for pipefitters.
3) If a
work permit is not issued during an emergency, what must be done to do the
work?
a.
Superintendent must approve.
b. All safety precautions must
be taken.*
c.
Wear Scott air Pak.
d.
Joint site inspection.
4) The
Receiver must be stop work if ………………. .
a.
He cannot find the issuer.
b. The work site becomes
unsafe.*
c.
The issuer leaves the site.
d.
The designated representative must leave.
5) Which
of the following is not a restricted area?
a.
Tank farm
b.
Loading pier.
c. Dump site. *
d.
Gasoline station.
6) What
is the purpose of the work permit system?
a.
To insure that hot work is not done in restricted area.
b. To authorize specific
construction or maintenance work. *
c.
To document where receiver start work for time keeping.
7) What
do you call an area where work permits are required?
a. Restricted area. *
b.
Sensitive area.
c.
Controlled area.
d.
Dangerous area.
8) Who
must sign a permit issued for to 30 days?
a.
Receiver and designated representative.
b. Operation and maintenance
division heads. *
c.
Designated representative
d.
Operations foreman, issuer and receiver.
9) Who is
the check list section important to issuer and receiver.
a.
It tells them all the precautions to take.
b. It make sure important steps
have been taken.*
c.
It defines the duration and scope of work.
d.
It controls the receiver’s break time.
10) Which
work permit requires sewer to be covered within 75 feet?
a.
Entry
b.
Cold
c. Hot*
d.
Release
11) Who
is responsible for safety at the work site after a permit has been extended?
a.
The original issuer and receiver.
b.
The person who countersigned the permit.
c.
The one who originally did the joint site inspection
d. The issuer and receiver who
signed the extension.*
12) What
happens if work must continue past the time the original permit was to expire?
a. Extend the permit or issue a
new one.*
b.
Work can continue until the job is completed.
c.
Stop work and came back next day.
d.
Keep working but tell the issuer.
13) What
are the basic precautions for confined space entry, select all items that
apply.
a.
A sign a standby man, install lighting, install air mover.*
b. Take gas test.*
c. Isolate, clean and purge
equipment.*
d. Use PPE.*
14) A release
of hazardous liquids or gases permit is required when?
a.
Operators release hydrocarbons to the flare.
b.
Crafts man builds a scaffold.
c. Pipefitters open a line or
install blinds.*
d.
Operation drain equipment.
15) What
hazard would you find when doing hot work?
a.
Auto ignition temperature.
b. Ignition source.*
c.
Ignition switch.
d.
Ignition point.
16) We
use work permit in hazardous areas to identify …………
a.
Expired permit.
b.
Alternated representative.
c.
The designated representative.
d. Hazards and precautions.*
17) The
use of a vehicle in an operating area requires, which work permit?
a.
Entry
b. Hot *
c.
Cold
d.
Release
18) What
are the basic precautions for cold work? Select all items that apply?
a.
Gas test.
b. PPE, barricade and warning
signs.*
c.
Special work precautions.
d.
Standby man.
e.
Fire watch.
19) What
is oxygen deficiency?
a. A lower than normal amount of
oxygen. *
b.
Higher than normal amount of oxygen.
c.
Less 23.5% oxygen.
d.
Oxygen that above it’s flash point.
20) What
are the basic precautions for hot work permit? Select all items that apply?
a. Blind, isolate, clean and
purge equipment.*
b. Fire watch.*
c. Fire protection equipment*
d. Cover sewer drains.*
e. Gas test.*
21) What
is the acceptable level of LEL to allow hot work?
a.
10 to 100 PPM.
b. 0.0 PPM. *
c.
5% to 50%
d.
21% to 23.5%
22)
Select the statement where all THREE items are needed before allowing entry
into a confine space?
a.
Air mover, respirators and countersignatures.
b.
Fire watch, air mover, gas test.
c.
Gas test. Fire extinguisher, barricades.
d. Lighting, standby man, air
mover. *
23) The
receiver can leave the job site any time as long as he gets the permeation from
his supervisor.
a.
True
b. False *
24) Who
should keep the work permit?
a.
The standby man.
b. The receiver and issuer.*
c.
Fire watch.
d.
Craft man.
25) What
should be a assigned when working near combustible materials?
a.
Standby man
b. Fire watch *
c.
Fire man
d.
Flag man
26) What
training should a fire watch have?
a.
Operate heavy equipment.
b.
Operate control room.
c. Operate fire equipment.*
d.
Operate radio equipment.
27) Who
should ask for work permit before they start working?
a.
The standby man.
b. The receiver.*
c.
The fire watch.
d.
The issuer.
28) Who
should point out all hazards and write on the work permit?
a. The issuer.*
b.
The standby man.
c.
The fire watch
d.
The receiver.
29) Who is responsible for the safety on the
work site?
a.
The receiver.
b.
The issuer.
c. Both issuer and receiver.*
d.
Both fire watch and the standby man.
30) What
is the purpose of the joint site inspection?
a.
To check the availability of equipment and man power.
b.
To see the work plan and it is implementation.
c. To discuss the work and
identify any hazards and risk.*
d.
To meet the works and observe their activities.
31) What
must be checked during the joint site inspection? Select all items that apply.
a. Safety devices.*
b. Equipment condition.*
c.
Gas test.
d.
Attendance report.
32) Who
decides whether an area should be restricted or not?
a. The department manager. *
b.
The superintendent.
c.
The issuer.
d.
The receiver.
33) What
type of work does the work permit system authorize?
a. Specific construction,
maintenance or repair work.*
b.
All work constructed for Saudi Aramco.
c.
All work done by maintenance or contractors.
d.
Non-hazardous work where safety is important.
34) Who
is a work permit receiver?
a.
A qualified Saudi Aramco employee.
b. A person certified to receive
permit.*
c.
A person nominated by his supervisor.
d.
A maintenance or contract worker.
35) The
safety of work site is a sole responsibility of an issuer?
a.
True.
b. False.*
36) What
responsibility do issuers and receivers share when signing a work permit?
a.
Responding to emergency events.
b.
Monitoring the operation of process.
c. Maintaining safety conditions
at the site.*
d.
Getting countersignatures form superintendent.
37)
Restricted areas include which locations?
a. Gas plant, tank farms, and assembly areas.
b. Pump station, tank farms, and
gas well. *
c.
Dining halls housing unites, and operating area.
d.
Welding shops pump station, and assembly area.
38) Who
can decided that work is a low risk and that a work permit is not needed?
a. The superintendent. *
b.
The receiver.
c.
The department manager.
d. The issuer.*
39) Who
must sign the work permit to close it?
a.
Competent person.
b. Issuer and receiver. *
c.
Gas tester, issuer and receiver.
d.
Designated representative.
40) What
must the receiver do if he stops work?
a. Tell the senior crafts man.
b.
Tell the designated representative.
c. Tell the issuer. *
d.
Tell his immediate supervisor.
41) Work
permit can be issued for up to 30 days if ……….
a.
The work site is far away.
b.
Only cold work will be done.
c. It is highly unlikely that
conditions will change. *
d.
The receiver cannot close the permit.
42) Who
must sign a work permit to extend it?
a.
Superintendent’s countersignature is required.
b.
The new issuer, receiver and gas tester.
c. The new issuer and receiver.
*
d.
The new area foreman and the new issuer.
43) “use
a fire blanket” or “hand dig only” are example of what?
a.
Hazards.
b.
Precautionary hazards.
c.
Regular precaution.
d. Additional precautions. *
44) Work
permit authorize …………
a. Specific work at specific
location. *
b.
Specific tools at general location.
c.
General work at specific plant.
d.
General equipment at all work site.
45) Where
could an issuer find out which permit to issue for a special job?
a.
Facility operating instruments.
b.
On the front of any work permit.
c. On the back of any work
permit. *
d.
Corporate loss prevention manual.
46) The
information’s entered in the “extra work location” box is important because it
controls?
a.
What equipment the receiver can use.
b. Where the receiver can work.
*
c.
How long the receiver can work.
d.
How many worker can be at the job site?
47) What
considered cold work?
a. Sand removal and scaffold
building. *
b.
Brush painting and abrasive blasting.
c.
Scaffold building and grinding.
d.
Abrasive blasting and painting.
48) What
must the issuer do if a join site inspection is not done?
a.
Required barricades and warning sign.
b.
A sign a designated representative.
c.
Tell his foreman.
d. Write why not on the permit.
*
49) What
must the issuer write in the work permit?
a. Name, badge number and certificate expiry date.
b.
Gas test results, name and badge number.
c. Name, organization code and
badge number. *
d.
Badge number and certificate number.
50) What
information must the gas tester enter on the work permit?
a.
LTX-310 expiry date, name and badge number.
b.
Badge and certification number.
c.
Gas test results and normal level.
d. Gas test results, name and
badge number. *
51) Any
worker can be a sign as standby man?
a.
True
b. False. *
52) Why
must equipment be de-energized and depressurized before work is started?
a. Accidental start-up could
happen. *
b.
Purge gas can be lost.
c.
Locks and tags will deteriorate.
53) Who
install locks and tags first?
a.
contractor.
b.
Power distribution.
c.
Electrical engineer.
d. Operation. *
54)
Installing lock and tags on electrical breakers prevents accidental.
a.
Blind installation.
b. Start-up of equipment *
c.
Nitrogen release.
d.
Purging of equipment.
55) The
issuer must try to start-up equipment at the field switch after it has been
isolated and before work start to make sure.
a.
Locks and tags are installed.
b.
The receiver’s tag is installed.
c.
There is no tag in the area.
d. It cannot accidently start. *
56) How
can process equipment be cleaned?
a.
Treating and hydro cracking.
b.
Closing valves and adding locks
c.
Gas testing and steaming
d. Steaming and or water-
washing. *
57) Who
installs receiver’s locks?
a. One member from each work
crew. *
b.
The engineer and receiver.
c.
The issuer and receiver.
d.
Every member of the work crew.
58) When
operators change shifts.
a. Their keys are usually
transferred to the next shift. *
b.
Their tags must be erased.
c.
Their locks and tags must be removed.
d.
Their locks must be replaced.
59) We
isolate equipment to make sure it cannot be.
a.
Shut-down on purpose.
b.
Shut-down by accident.
c.
Taken to a shop for repair.
d. Started-up, leak or cause
electrical shock. *
60) Why
are hold tag installed?
a.
To record gas tests.
b.
To record accidents.
c. Explain why the lock is
installed? *
d.
To identify the issuer and receiver.
61) Removing
fuses form an electrical circuit or disconnecting electric wiring is an example
of what?
a.
Locking
b.
Cleaning.
c.
Purging.
d. Isolating. *